Glenn Arthur Arena: The demolition of the arena slab is complete, roof trusses have been scraped and repainted and the subgrade has been prepared to begin rebuilding the arena surface. Structural steel has been placed for the new windows to overlook this arena. The apron (perimeter of the rink) is largely complete and preparations for pipe infrastructure on the arena slab are in progress.
Bert Hall Arena: Though it started one month later, the demolition of Bert Hall Arena slab, stands and office/storage towers is complete. Roof trusses have been scraped and repainted and the subgrade is in the process of being reconstructed. The area for the two-level mezzanine structure has been excavated and reinforcing steel has been implemented for the foundation of this new structure.